Partner Information Update Edmonton-Calgary 500 kV Transmission Development .


58 views
Uploaded on:
Description
Today\'s Meeting - Purpose. Give industry partners introductory audit of undertaking status and exercises Discuss proposed upgrade process. Plan (9 AM to 11 AM). Presentation and connection (Neil Millar)Review of burden and era estimate data (Trevor Cline)Overview of general venture status (Andy Kneubuhler and Stephen Kane)Progress towards office application (Mark Johns)Review ace
Transcripts
Slide 1

Partner Information Update Edmonton-Calgary 500 kV Transmission Development September 29, 2005 Introduction Neil Millar, VP, Transmission - AESO

Slide 2

Today\'s Meeting - Purpose Provide industry partners with introductory audit of venture status and exercises Discuss proposed redesign handle

Slide 3

Agenda (9 AM to 11 AM) Introduction and setting (Neil Millar) Review of load and era figure data (Trevor Cline) Overview of general venture status (Andy Kneubuhler and Stephen Kane) Progress towards office application (Mark Johns) Review proposition for continuous data overhauls and partner criticism (Fred Ritter) Wrap-up

Slide 4

AESO Core Business Functions Operate Canada\'s first focused discount power showcase Direct the sheltered and dependable, ongoing operation of Alberta\'s interconnected electric matrix Plan the transmission framework and make game plans for redesigns and options Provide open and non-biased access to Alberta\'s transmission framework Coordinate and lead common settlement – about $5 billion in yearly vitality exchanges

Slide 5

Transmission Facility Owner Business Functions (AltaLink and EPCOR Transmission) Own, work and keep up existing resources Construct new transmission fortifications in light of heading from the AESO (after EUB endorsement of need application) Detailed outline and designing Securing particular privileges of-way Develop Facility Applications and get "Allow and License" from EUB

Slide 6

Project Need: Generation in North Load development Red Deer & southern Alberta Over a long time since hall was strengthened Coal Gas Hydro Wind

Slide 7

Edmonton–Calgary Reinforcement Key Elements S-KEG Lines Conversion to 500 kV (Keephills-Genesee-Ellerslie) New 500 kV line (Genesee to Langdon) Benefits Necessary to dependably serve Alberta (Red Deer & south) Remove hindrances to new era Significant line misfortune reserve funds

Slide 8

Progress To Date AESO recorded Need Identification report in May 2004 with EUB hearing in December 2004, shutting in January 2005 EUB Approval of Need got in April 2005

Slide 9

Stakeholder Information Update Edmonton-Calgary 500 kV Transmission Development September 29, 2005 Review of Load and Generation Forecast Trevor Cline, director, Central System Planning - AESO

Slide 10

Load conjecture increment - Alberta Internal Load anticipated that would surpass 13,700 MW by 2015; an expansion of 1,800 MW because of quick oil sands development TransAlta is requesting that the EUB alter its 900 MW Centennial allow to take into account the development of a littler 450 MW plant All Clover Bar units are to be resigned before 2006 Wind era demands have expanded over the gauge Proposed Bow City two-unit 1000 MW coal plant for southern Alberta proceeds with improvement with open exposure in January and open houses in March 2005 Calgary territory capacitor banks affirmed and will be in-administration by February 2006 Forecast Update What\'s changed since the Need application

Slide 11

Total twist era to be introduced by 2010 expanded from 800 MW to 1500 MW in the vicinity era and load expanded All Clover Bar units resigned before 2006 New 500 MW coal plant included southern Alberta in 2010 Completion date for third coal unit at Keephills changed from 2009 to 2011 Forecast Update Adjustments made to the estimates for this upgrade

Slide 12

5,400 MW of new era required by 2015 to fill the crevice Forecast Update Supply-Demand Gap

Slide 13

Winter ability surpassed in 2009 Forecast Update Need Timing: Need is currently. The AESO will have interval measures set up to guarantee unwavering quality prerequisites are addressed between the need date and the in-administration date. Summer ability surpassed in 2007

Slide 14

Forecast Update Congestion on the Edmonton to Calgary way Interim measures & change of S-KEG will lessen blockage to under 5% If no new substantial units go into administration in the north, way clog conjecture to be 10% amid the late spring hours of 2009

Slide 15

Capability increment in Edmonton to Calgary transmission capacity is required before the late spring of 2007 in this manner early transformation of the S-KEG is still required Increase in Edmonton to Calgary transmission capacity is still required as quickly as time permits to address both unwavering quality concerns and blockage The AESO is executing interval measures that will cross over any barrier between the need today and when the new offices will be set up Forecast Update No effect on venture plan

Slide 16

Questions?

Slide 17

Stakeholder Information Update Edmonton-Calgary 500 kV Transmission Development September 29, 2005 Overall Project Status Andy Kneubuhler, supervisor, 500 kV Projects - AESO Stephen Kane, senior venture director - AltaLink

Slide 18

500 kV Project Components South-KEG 500 kV Conversion One 500/240 kV transformer bank at Keephills by AltaLink Two 500/240 kV transformer banks at Ellerslie by AltaLink Conversion of 1203L and 1209L by AltaLink Conversion of Genesee substation by EPCOR Transmission Conversion of three Genesee unit transformers by era proprietors

Slide 19

500 kV Project Components Genesee to Langdon 500 kV Line end at Genesee by EPCOR Transmission Line end at Langdon by AltaLink 1205L option by AltaLink

Slide 20

AESO Progress to September Engineering studies to characterize gear capacity and abnormal state determinations Transformer limit and over-burden necessities Phase shifter limit and point go Fault level reviews Coordinate exercises between TFO\'s (AltaLink & EPCOR Transmission) Hold month to month extend coordination gatherings Develop a practical particular for every venture Develop extend checking and revealing procedures

Slide 21

Project Cost Evaluation Budget gauge from the Need Application is in 2004 dollars The TFO gauges going with the Proposal to Provide Service (PPS) and consequent upgrades will be in end-of-venture dollars S-KEG fruition November 2007 Genesee to Langdon Line consummation September 2009 Developing a monetary following technique to permit examination of expenses to the financial plan on a continuous premise

Slide 22

Project Scope Refinements and Cost Estimates Detailed building movement will give redesigned data and enhanced gauge exactness AESO utilitarian particular and TFO Proposal to Provide Service characterizes the venture scope Assessing the effect of patterns in transmission materials, significant hardware and development costs on the venture Updated cost data will be imparted to partners before year end

Slide 23

EUB Need Approval Amendment Detailed designing has prompted to the need to record an alteration application with the EUB The AESO\'s application will contain the subtle elements of the required change and related cost and the advantages The application will be documented in October and accessible to partners around then

Slide 24

Amendment Application Overview Change Keephills and Ellerslie transformers from 750 MVA three-stage units to 1200 MVA single-stage units Transformer size was returned to subsequently of extra designing reviews The revision will give insight about the advantages and costs; a portion of the advantages include: upgraded misfortune reserve funds enhanced working adaptability and future limit less effect on producing plants taking after possibilities

Slide 25

Questions?

Slide 26

AltaLink Update South KEG 500 kV Conversion

Slide 27

South KEG Conversion Update Progress since Need endorsement Engineering thinks about Transformer revision concentrates Short circuit & stack stream concentrates Functional determination input

Slide 28

South KEG Conversion Update Progress since Need endorsement (cont\'d) General Project Management "Pattern" extension, calendar and gauge Project execution arrange advancement Detailed specialized degree improvement AltaLink extend group set up Coordination with EPCOR Transmission Project chance administration handle actualized Preparation for Proposal to Provide Service (PPS) accommodation to AESO

Slide 29

South KEG Conversion – Schedule AESO Need Approved April/05 Landowner Consultation Begins July/05 Functional Specification Complete Oct/05 +20% - 10% Estimate Nov/05 Proposal to Provide Service Nov/05 Facility Application Jan/06 Permit and License June/06 Equipment & Material Procurement July/06 Construction Start Sept/06 +10% - 10% Estimate Nov/06 In-administration Date Nov/07

Slide 30

Questions?

Slide 31

Genesee to Langdon 500 kV Line

Slide 32

Genesee to Langdon 500 kV Line Progress since Need endorsement Engineering concentrates Meteorological review finished Tower family improvement Line streamlining concentrate Functional particular info

Slide 33

Genesee to Langdon 500 kV Line Progress since Need endorsement (cont\'d) General Project Management "Benchmark" extension, timetable and gauge Project execution arrange advancement Detailed specialized determination advancement AltaLink extend group set up Coordination with EPCOR Transmission Project chance administration handle actualized

Slide 34

Genesee to Langdon 500 kV Line – Schedule AESO Need Approved April/05 Landowner Consultation Begins July/05 Functional Specification Complete Oct/05 +20% - 10% Estimate Apr/06 Proposal to Provide Service Apr/06 Facility Application June/06 Permit and License Dec/06 Equipment & Material Procurement Jan/07 +10% - 10% Estimate March/07 Construction Start June/07 In-administration Date Sept/09

Slide 35

Questions?

Slide 36

Stakeholder Information Update Edmonton-Calgary 500 kV Transmission Development September 29, 2005 Progress Towards Facility Application Mark Johns, director, Conceptual Engineering and Siting - AltaLink

Slide 37

Siting Overview What are we attempting to finish Determine the most appropriat

Recommended